By Brian Haughey • Updated 2026-11-16
To hit install dates on several custom cabinet jobs at once, schedule each job backward from its install date, give every stage a working-day duration, and check the total build hours against what your shop can actually produce each week. Then review the schedule once a week and move dates as soon as something slips, not on install day. A whiteboard can show where jobs are, but it can't do the backward math, add up hours, or warn you when a stage runs late.
I ran a custom cabinet shop for over 20 years, and most of what's below came from getting this wrong before getting it right. If you're comparing scheduling tools rather than learning the method, see the best cabinet shop scheduling software. For the bigger picture of how a shop schedule fits together, see cabinet shop scheduling.
It's usually not the build. A missed install date almost always traces back to something that happened weeks earlier. Four things cause most of them:
Start with the install date and count backward in working days, one stage at a time. Working backward shows you whether the date is possible before you've promised it.
If the backward math puts the start of production in the past, the install date can't be met. Say so now. It's a much easier conversation today than it will be the week before install.
Count hours, not jobs. Two jobs can mean very different loads, and "we've got three jobs going" tells you almost nothing about whether a fourth will fit.
Here's a simple example. Say a shop has 4 people on the floor, and each gets about 30 productive hours a week after cleanup, interruptions, and deliveries. That's roughly 120 build hours a week.
| Job | Estimated shop hours | Weeks of capacity |
|---|---|---|
| 28-box kitchen | 140 | 1.2 |
| Two baths and a laundry | 60 | 0.5 |
| Built-in bookcases | 35 | 0.3 |
| Total | 235 | about 2 weeks |
That's about two weeks of work already on the books. If another kitchen wants to be in production during those same two weeks, something has to move. Use your own estimated hours per stage. Better yet, if you track actual hours on past jobs, use those, because actuals usually run higher than estimates.
Keep it short and keep it regular: fifteen minutes, same day each week, with the owner and whoever runs the office.
The point is to catch a three-day slip while it's still only three days.
Treat it like a new job entering the schedule. Shift that job's stage dates by the change, then check the weeks it now lands in against your capacity. If moving it earlier pushes another job late, the client who asked for the change hears about it first. The client who didn't ask shouldn't be the one who pays for it.
Not always. For two or three jobs at a time, a spreadsheet with stage dates works fine, as long as someone keeps it current. Past that, the problems from the top of this article come back: dates live in one person's head, slips show up late, and the crew can't see what's next without asking. (More on that point in when a cabinet shop outgrows the spreadsheet.)
Whatever tool you pick, look for these:
General project tools like Monday or Trello can hold stage dates, but you set up the cabinet stages and the date math yourself. A shop ERP such as Innergy goes further into production planning, with a bigger price and a longer setup. If you need machine-level scheduling, look there: Cabinetshop Maestro doesn't schedule machines.
Cabinetshop Maestro is job management software built for custom cabinet shops. It tracks jobs from lead to install with workflow boards, scheduling, tasks, and client communication. To schedule a job, you pick the install or end date, and Maestro builds the timeline from your saved default, spreading stages backward in working days and skipping weekends based on your settings. Stages that pass their end date with open tasks get flagged, you can shift a whole job forward or back in one step, and approved time off shows up on the task calendars. Pricing is flat per tier, $199 a month for Professional or $399 for Enterprise, with a 14-day free trial.
For more on keeping the rest of the job straight, read how to keep cabinet jobs organized. From the guide: "We're always scrambling to meet deadlines".
Add your current backlog to this job's own stage durations, then add a buffer. If you have three weeks of work queued and the job needs four weeks start to finish, the earliest honest date is about seven weeks out.
One to three working days before install covers most jobs. Add more for outside finishing, imported hardware, or anything with a long lead time.
Both. Set dates by job, counted backward from install. Then look across all jobs by stage to see when finishing or assembly is about to get overloaded.
Materials arriving late. Usually that's because the deposit came in late or the order went out after cutting was supposed to start.
Put the schedule somewhere the crew can see it without asking, and have them mark tasks done as they finish. A schedule only the office updates drifts away from what's actually on the bench.
It shows where jobs are today, which is useful. It doesn't count working days, total hours, or warn you about a late stage, so it works best next to a real schedule, not instead of one.
No. Maestro schedules jobs and stages in working days, and you change dates by editing them. Machine time is still planned by you.
Nothing to download, nothing to install, and no contracts.